Watagan bridge

Client:

Cessnock City Council

Estimated Value:

1.5 million

Location:

Watagan No.1 Bridge

Completion Date:

13 Week Project - Completed August 2024

Services Provided:

Bridge construction, replacement and maintenance, Project and contract management, Road construction and associated works, Drainage and stormwater, maintenance and construction

Watagan Bridge was constructed as a 14m long dual lane bridge utilising PSC precast planks with castellated kerbs and approach slabs. During construction, a temporary bridge was installed to maintain local traffic. The new bridge was raised 1m for flood immunity including 200m of road pavement works to tie in the approaches.